1,718 tons of supply, manufacture and assembly of metallic structures in the following areas: preheater building; galleries for the transport of clinker, up to 135 m high.
2,301 tons of mechanical equipment assembly: preheater building; homogenization silos; crushing, transportation and storage of additives; cement mill no. 4; feed to the preheater.
1,131 tons of supply, manufacture and assembly of pipelines in: cooler and main collector; raw material mills.
372,000 m3 excavation and embankments of stone materials, loading, hauling, homogenizing, laying and compacting to form a platform for railroad tracks, interior roads and buildings.
6,436 m of railings on platforms, galleries, bridges.
252 tons of supply, qualification and placement of anti-skid plate.
6.724 m2 sheet for roofs and facades.
2,208 tons of metal structure assembly in the preheater building.
4,015 m2 grid type ensa for platforms and stair landings.
3,508 tons of supply and application of paint and sand blast for structures, ducts, chutes and railings.