Metallic Structures: Supply, manufacture and assembly of 1,382 tons for the triodetic cover of the Palletizing Building; for the support structure racks of services; for galleries to support clinker conveyors and warehouse (bunker); for the support galleries of the cement transport; support structure for refractory brick in clinker cooler; fine hopper support; triodetic cover of the tiling area.
Mechanical Assembly: 870 tons of mechanical equipment assembly for cement belt conveyors; primary and secondary crusher, screens, metal detectors, belts, motors; traveling cranes, 950 m long roller conveyor belt.
Ensa grid: 722 m2.
Mesh steps: 385 pieces.
Handrails: 1,024 m.
Sheet: 2,430 m2 for roofs and facades of buildings and galleries.
Civil Works: 3,120 m2 Crushing Product Material to complement the embankment by erosion and runoff for the FFCC tracks includes hauling, laying, leveling and banding with a bulldozer
Service: Provision of personnel for technical support of testing and commissioning of mechanical equipment for the areas of cement mills, additives park, clay park, crushing, cement warehouse and dry pozzolan silo.